Compensation
|
Market rate only.
|
For a
typical rural household that owns the average of 3 acres of land, the Act
will replace the loss of annual average per capita income of Rs.11,136 for
the rural household, with:
- four
times the market value of the land, and
- an
upfront payment of Rs.1,36,000 (US$ 3,000) for subsistence,
transportation and resettlement allowances, and
- an
additional entitlement of a job to the family member, or a payment of
Rs.5,00,000 (US$ 11,000) up front, or a monthly annuity totaling
Rs.24,000 (US$ 550) per year for 20 years with adjustment for inflation
– the option from these three choices shall be the legal right of the
affected land owner family, not the land acquirer, and
- a
house with no less than 50 square meters in plinth area, and
- additional
benefits may apply if the land is resold without development, used for
urbanization, or if the land owner belongs to SC/ST or other protected
groups per rules of the Government of India
If the
affected families on the above rural land demand 100% upfront compensation
from the land acquirer, and the market value of land is Rs.1,00,000 per acre,
the Act mandates the land acquirer to offset the loss of an average per
capita 2010 income of Rs.11,136 per year created by this 3 acre of rural
land, with the following:
- Rs.18,36,000
(US$ 41,727) to the rural land owner; which is the total of R&R
allowances of Rs.6,36,000 plus Rs.12,00,000 – which is four times the
market value of the land, plus
- a
house with no less than 50 square metres in plinth area and benefits
from Schedule III-VI as applicable to the rural land owner, plus
- additional
payments of Rs.6,36,000 each to any additional families claiming to have
lost its livelihood because of the acquisition, even if they do not own
the land
(Source
Wikipedia and PDF document)
|
Same in
addition, the ordinance has brought 13 land
acquisitioning acts left in LARR 2013 bill under its ambit, thereby
increasing the number of beneficiaries.
The
LARR Act 2013 exempted 13 laws (such as the National Highways Act, 1956 and
the Railways Act, 1989) from its purview. However, the LARR Act 2013 required
that the compensation, rehabilitation, and resettlement provisions of these
13 laws be brought in consonance with the LARR Act 2013, within a year of its
enactment, through a notification. The Ordinance brings the compensation,
rehabilitation, and resettlement provisions of these 13 laws in consonance
with the LARR Act 2013.
(Source -
PRS legislative research)
|
|
Expanding the Categories
|
-
|
The
LARR Act 2013 requires that the consent of 80% of land owners is obtained for
private projects and that the consent of 70% of land owners be obtained for
PPP projects.
|
The
Ordinance exempts five categories from this provision of the Act. The five
categories are defence, rural infrastructure, affordable housing, industrial
corridors and infrastructure projects including Public Private Partnership
(PPP) projects where the central government owns the land.
|
|
Social Impact Study and acquisition of
multicropped land and irrigated land beyond certain limits
|
-
|
LARR 2013 - these are applicable to all types of
acquisition.
|
Applicable
to all types except - The
five categories - defence, rural infrastructure, affordable
housing, industrial corridors and infrastructure projects including Public
Private Partnership (PPP) projects where the central government owns the
land.
|
|
Return of unutilized land.
|
|
The
LARR Act 2013 required that if land acquired under it remained unutilised for
five years, it was returned to the original owners or the land bank.
|
Ordinance
states that the period after which unutilised land will need to be returned
will be five years, or any period specified at the time of setting up the
project, whichever is later.
|
|
Period of retrospective application
|
-
|
The
LARR Act 2013 states that the Land Acquisition Act, 1894 will continue to
apply in certain cases, where an award has been made under the 1894 Act.
However, if such as award was made five year or more before the enactment of
the LARR Act 2013, and the physical possession of land has not been taken or
compensation has not been paid, the LARR Act 2013 will apply.
|
Ordinance
states that in calculating this time period, any period during which the
proceedings of acquisition were held up: (i) due to a stay order of a court,
or (ii) a period specified in the award of a Tribunal for taking possession,
or (iii) any period where possession has been taken but the compensation is
lying deposited in a court or any account, will not be counted.
|